Location: Dearborn, MI
Customer Challenge: Steel customer had a severely damaged precipitator stack from 1963 that was relevant to production for repairs or replacement.
Solution: The original concept was to plate clad all eroded/corroded areas while steel production continued. Upon closer NDE examination, it was determined that the most cost effective decision was replacement. Monarch responded by fabricating and then installing a replacement during a scheduled 48 hour outage.