Mid Michigan Boiler House

Location:     Midland, MI
 
Customer Challenge:    Mid Michigan utility had a contract obligation to supply steam to a neighboring facility and did not have sufficient capacity. 
 
Solution:      Monarch was contracted to complete all phases of construction on a fast track basis.  From the ground up, six boilers were installed with a combined capacity of over 1.5 million lbs. of steam per hour.  All auxiliary equipment was installed including 520 tons of structural steel, 19,000 LF of piping and a 31,000 sq. ft. building.  On site manpower peaked at 400 tradesmen.  The contract value was $43 million. 